If you choose the help of ITCertMaster, we will spare no effort to help you pass the exam. Moreover, we also provide you with a year of free after-sales service to update the exam practice questions and answers. Do not hesitate! Please select ITCertMaster, it will be the best guarantee for you to pass PMP certification exam. Now please add ITCertMaster to your shopping cart.

ITCertMaster IT Certification has years of training experience. ITCertMaster PMI PMP exam training materials is a reliable product. IT elite team continue to provide our candidates with the latest version of the PMP exam training materials. Our staff made ​​great efforts to ensure that you always get good grades in examinations. To be sure, ITCertMaster PMI PMP exam materials can provide you with the most practical IT certification material.

ITCertMaster is a website for PMI certification PMP exam to provide a short-term effective training. PMI PMP is a certification exam which is able to change your life. IT professionals who gain PMI PMP authentication certificate must have a higher salary than the ones who do not have the certificate and their position rising space is also very big, who will have a widely career development prospects in the IT industry in.

Exam Code: PMP
Exam Name: Project Management Professional
Guaranteed success with practice guides, No help, Full refund!
PMI PMP Exam Questions 3615 Q&As
Updated: 2014-10-10
PMP Exam Prep Detail : Click Here

If you buy ITCertMaster PMI PMP exam training materials, you will solve the problem of your test preparation. You will get the training materials which have the highest quality. Buy our products today, and you will open a new door, and you will get a better future. We can make you pay a minimum of effort to get the greatest success.

Add ITCertMaster's products to cart now! You will have 100% confidence to participate in the exam and disposably pass PMI certification PMP exam. At last, you will not regret your choice.

PMP Free Demo Download: http://www.itcertmaster.com/PMP.html

NO.1 The Risk of NOT meeting project quality objectives:
A. considered a long term risk.
B. can be minimized through continuous monitoring.
C. All of the other alternatives apply.
D. will be reflected in the "in-service" life of the product or service.
E. Considered a long term risk and will be reflected in the "in-service" life of the product or service.
Answer: C

PMI certification   PMP Test Questions   PMP exam simulations   PMP Training online   PMP exam

NO.2 As the project manager, you are preparing your methods for quality management. You are
looking for a method that can demonstrate the relationship between events and their resulting
effects. You want to use a method to depict the events that cause a negative effect on quality. Which
of the following is the BEST choice for accomplishing your objective?
A. Histogram
B. Pareto chart
C. Ishikawa diagram
D. Control chart
Answer: C

PMI Exam Cram   PMP VCE Dumps   PMP Latest Dumps   PMP exam prep   PMP

NO.3 You assigned staff members to activities, estimated work and scheduled your project. Then, you
depicted the following resource histogram for your staff:
Exhibit:
What is the diagram telling you?
A. You may run into problems with dual reporting relationships.
B. You may be able to finish the project early by reassigning work.
C. The project can probably not be finished as scheduled.
D. You should avoid network logic diagramming for scheduling.
Answer: C

PMI VCE Dumps   PMP test questions   PMP Test Answers   PMP pdf

NO.4 You are the project manager within an information technology department of a large retailer
In order to allow for better real-tracking, in inventory control, and supply chain management, in
inventory control, and supply chain management, your company in financing a project to install and
to install and deploy RFID on all items of merchandise. As the project manager, you've just completed
the select sellers' process, and selected 5 different vendors on your qualified sellers list who has
responded to your company's RFP. One of the vendors remaining the qualified sellers list is RFID-PM
Inc. although you have no financial interest in this company, one of yours old high school buddies,
Terence, sits on the board of directors of this company. Is there a conflict of interest in this situation?
A. In order to protect your privacy, you only have to disclose your relationship with RFIDPM, Inc. if
you are directly questioned
B. Because of your friendship with Terence, a conflict of interest exist that must be disclosed
immediately
C. Depending on the depth of your friendship with Terence, a conflict of interest could exist
D. Since neither you nor your family members has any financial interests in this company there is no
conflict of interest
Answer: D

PMI Practice Exam   PMP study guide   PMP Test Questions

NO.5 A company is about to begin work on a large construction project to build four new buildings
for a bank that wants to open new branches. The sponsor is writing a project charter. She recalls that
a previous project the company performed for another bank ran over budget because the team had
underestimated the effort required to install the reinforced walls in the vault. The previous project
manager had documented the details of the lessons learned from this project. Where should the
sponsor look for these lessons learned?
A. The company's organizational process assets
B. The project records management system
C. The project's work performance information
D. The project's performance reports
Answer: A

PMI practice test   PMP certification   PMP Exam Prep   PMP certification training   PMP
Explanation:
Lessons learned from past projects are always part of a company's organizational process assets, and
are usually stored in a process asset library. The other three answers are important project tools, but
they're not where you find lessons learned.

NO.6 A project manager is creating a risk response plan. However, every time a risk response is
suggested, another risk is identified that is caused by the response. Which of the following is the BEST
thing for the project manager to do?
A. Document the new risks and continue the Plan Risk Responses process.
B. Make sure the project work is better understood.
C. Spend more time making sure the risk responses are clearly defined.
D. Get more people involved in the Identify Risks process since risks have been missed.
Answer: A

PMI questions   PMP Bootcamp   PMP answers real questions   PMP   PMP

NO.7 Key Management skills include:
A. Negotiating
B. All of the other alternatives apply
C. Leading
D. Communicating
Answer: B

PMI   PMP certification training   PMP Exam Tests   PMP
Explanation:
All options are key management skills.

NO.8 During what Time Management Process are the specific activities that must be performed to
produce the deliverables in the WBS identified and documented?
A. Estimate Activity Durations
B. Define Activities
C. Sequence Activities
D. Develop Schedule
Answer: B